Skip to main content
VA Horizon
Book a Call
Permitting & Interconnection

What Happens Between a Signed Contract and Permission to Operate

Quick answer

Industry experts put the full timeline from a signed solar contract to Permission to Operate, the utility’s final sign-off, at roughly 60 to 90 days. It breaks into four stages: scheduling and design (1 to 2 weeks), permitting (2 to 4 weeks), physical installation (1 to 3 days of work, plus possible crew-scheduling delay of 1 to 2 weeks), and inspections plus utility interconnection (1 to 4 weeks, with utility review alone ranging from around 14 days at Duke Energy to 30 or more days at some California utilities).

Of those four stages, only one is meaningfully within the homeowner’s own control: reviewing and approving the system design promptly during the scheduling and design phase. Permitting and utility interconnection run on the AHJ’s and the utility’s own internal timelines regardless of how responsive anyone else is.

The Full Timeline, Stage by Stage

Scheduling and design comes first, typically 1 to 2 weeks, where the installer finalizes the system layout and the homeowner reviews and signs off on it. Permitting follows, typically 2 to 4 weeks, reviewed by the local Authority Having Jurisdiction rather than the utility. Physical installation itself is fast, just 1 to 3 days of actual work, though crew-scheduling availability can add another 1 to 2 weeks before that work starts. Inspections and utility interconnection close out the process, typically 1 to 4 weeks, ending in Permission to Operate, the utility’s own sign-off that the system can turn on.

Added together, industry experts describe the full window from a signed contract to a system actually turning on as roughly 60 to 90 days. That is the number a sales team should be quoting at signing, not a specific date.

The One Stage the Homeowner Genuinely Controls

Of the four stages, scheduling and design is the one a homeowner can meaningfully speed up, simply by reviewing and approving the proposed system design promptly instead of sitting on it. Permitting and utility interconnection do not work the same way. Both run on the AHJ’s and the utility’s own internal review timelines, and a homeowner calling to check in daily does not move either process along.

That distinction is worth stating plainly, because it tells a homeowner exactly where their own responsiveness matters and where it genuinely does not, rather than leaving them to assume every delay is something they could have prevented.

Want this handled for you?

Exclusive, confirmed solar appointments. $300 setup + $249 per booked appointment.

Book a Solar Call

Why Setting This Expectation at Signing Prevents a Bad Week Six

A homeowner who hears the full 60-to-90-day range at signing, broken into its four stages, understands why week five without a live system is normal rather than alarming. A homeowner who is not told that range at all tends to assume something has gone wrong the moment the process runs past a rough mental estimate of a few weeks.

Utility interconnection specifically deserves a mention at signing, since it varies more than any other stage, ranging from around 14 days at Duke Energy to 30 or more days at some California utilities. A homeowner in a slower utility’s territory should hear that upfront, not discover it by calling in confused near the end of the process.

What a Sales Team Can Say With Confidence, and What They Cannot

A sales team can confidently say the full process typically runs 60 to 90 days from signed contract to Permission to Operate, broken into scheduling and design, permitting, installation, and utility interconnection. A sales team cannot confidently promise an exact date, because two of the four stages, permitting and interconnection, run on local government and utility timelines outside the installer’s or the sales team’s control.

The honest version of this conversation sets a range, names the one stage the homeowner can actually influence, and flags upfront that utility territory is the single biggest source of variation in how long the last stage takes.

What this means for you

  • The full signed-contract-to-Permission-to-Operate timeline runs roughly 60 to 90 days across four stages: scheduling and design, permitting, installation, and utility interconnection.
  • Scheduling and design is the one stage a homeowner can meaningfully speed up; permitting and utility interconnection run on AHJ and utility timelines regardless of responsiveness.
  • Utility interconnection is the single biggest source of timeline variation, ranging from about 14 days at Duke Energy to 30 or more days at some California utilities.

Sources

The external data in this guide draws on the sources below. Figures described in the text as estimates or industry triangulations are directional and are not attributed to a single dataset.

FAQ

How long does it take from signing a solar contract to the system going live?
Industry experts put the full timeline at roughly 60 to 90 days, broken into scheduling and design (1 to 2 weeks), permitting (2 to 4 weeks), installation (1 to 3 days of work, plus possible scheduling delay), and inspections plus utility interconnection (1 to 4 weeks).
What is the single biggest variable in the solar installation timeline?
Utility interconnection. Permission to Operate review alone ranges from around 14 days at Duke Energy to 30 or more days at some California utilities, a wider spread than any other stage in the process.
Can a homeowner speed up their own solar installation timeline?
Only at one stage. Reviewing and approving the system design promptly during the scheduling and design phase is the one part of the process a homeowner can meaningfully influence. Permitting and utility interconnection run on the AHJ’s and the utility’s own internal timelines regardless.
Why might my neighbor’s solar installation go faster than mine?
Permitting and interconnection timelines depend on the specific local AHJ and utility territory, which can vary even between nearby properties, plus any added review layers like an HOA. A faster neighbor does not mean anything went wrong with a slower install.
What should a sales team tell homeowners about installation timing at signing?
State the full 60-to-90-day range upfront, broken into its four stages, name scheduling and design as the one stage the homeowner can influence, and flag that utility territory is the biggest source of variation in how long the final stage takes.

Set the expectation at signing. We will set the appointment before that.

Book a 15-minute call. $300 setup and $249 per booked, double-confirmed appointment, so the only clock your team is waiting on is the AHJ’s and the utility’s.

Book a Solar Call

$300 one-time setup · $249 per booked appointment · No-shows replaced free